Inspection Information:
Facility Type: | WS3 |
Inspection type: | Routine |
Inspection date: | July 02, 2019 |
Follow-up Required: | Yes |
This facility was given a moderate hazard rating.
More information on hazard ratings.
Violations:
A summary of the violations found during the inspection are listed below.
Code | Description / Observation / Corrective Action |
320 | Other (specify below) Observation: A Construction Permit is required prior to commencing any alterations, upgrades or extensions to a water supply system. A Construction Permit Application was not submitted to Northern Health prior to installing the new water supply system. Corrective Action: Submit a Construction Permit Application to the EHO or public health engineer by July 16, 2019. EHO to provide assistance in completing the construction permit application. |