Bread Garden Urban Cafe and Lounge - Inspection Report

Inspection Information:
Facility Type:Restaurant
Inspection type:Follow-Up
Inspection date:July 16, 2010
Number of critical violations:1
Number of non-critical violations:  3
Follow-up Required:  No

Violations:
A summary of the violations found during the inspection are listed below.

Code   Description / Observation / Corrective Action
105  Critical Inadequate Cooling & Refrigerated Storage of Potentially Hazardous Food(s)
Observation: Far display cooler (for sandwiches and wraps is running at 12 degrees Celsius as measured by a probe thermometer.
Corrective Action: All food removed from cooler at time of inspection. Do not use this cooler until it has been repaired and maintains food at 4 degrees Celsius or below.
112   Poor Sanitary Design, Construction, Installation of Equipment & Utensils
Observation: Sanitizer buckets on the service line do not contain the required concentration of sanitizer.
Corrective Action: Sanitizer replaced at time of inspection. Ensure sanitizer buckets reach 200ppm quats - to accomplish this they must be changed regularly throughout the day. Also make sure all staff are trained to rinse the sanitizer off the utensils before using them.
115   Inadequate Insect / Rodent Control
Observation: A screen door is still required.
Corrective Action: Provide a screen door.
130   Inadequate Sanitation Plan
Observation: A list of FoodSafe trained individuals is still required.
Corrective Action: Provide a list of FoodSafe trained individuals.
130   Inadequate Sanitation Plan
Observation: A written cleaning checklist is still required.
Corrective Action: Provide a written cleaning checklist that is specific to the areas of this premises that require routine cleaning. Include daily monitoring of glasswasher sanitizer concentrations through the use of chemical test strips -(samples of test strips provided at the time of inspection).

Comments:

Pepsi cooler has been repaired and now maintains food at 4 degrees throughout as required. Temperature logs have been made this date to reflect all cooling and hot holding but have yet to be implemented. Glasswasher still requires repairs, the dishwasher is being used for glasswashing in the interim.