Inspection Information:
Facility Type: | Swimming Pool/Waterslide (>19 sq.m) |
Inspection type: | Routine |
Inspection date: | February 17, 2015 |
Follow-up Required: | Yes |
This facility was given a moderate hazard rating.
More information on hazard ratings.
Chlorine (Total) |
Chlorine (Free Available) 0 |
Chlorine (Combined) |
Bromine (Free Available) |
pH >8.0 |
Total Alkalinity 95 ppm |
Total Hardness |
Temperature 28.9°C |
Clarity Clear |
Cyanuric Acid |
Violations:
A summary of the violations found during the inspection are listed below.
Code | Description / Observation / Corrective Action |
101 | Improper Water Chemistry/Water Clarity Observation: FAC measured 0 ppm at the time of inspection. This was corrected at the time of inspection to 2.5 ppm. Corrective Action: Please ensure chlorine levels are maintained at a minimum of 1.5 ppm, ideally between 1-3ppm. |
101 | Improper Water Chemistry/Water Clarity Observation: pH measured over 8 at the time of inspection. This was corrected to 7.6 at the time of inspection. Corrective Action: Please ensure the pH is maintained between 7.2-7.4. |
104 | Improper Turnover of Flow Rate Observation: Flow metre was observed to be inoperable at the time of inspection. Corrective Action: Repair or replace as needed to ensure flow metre is able to correctly display the flow. |
307 | Improper Storage of Chemicals Observation: Chemical containers are being re-used to store different chemicals (and was observed to be stored in chlorine containers). Corrective Action: Discontinue this practice immediately. Mixing of chemicals can result in formation of toxic fumes or fires. |
101 | Improper Water Chemistry/Water Clarity Observation: FAC measured 0 ppm at the time of inspection. This was corrected at the time of inspection to 2.5 ppm. Corrective Action: Please ensure chlorine levels are maintained at a minimum of 1.5 ppm, ideally between 1-3ppm. |
101 | Improper Water Chemistry/Water Clarity Observation: pH measured over 8 at the time of inspection. This was corrected to 7.6 at the time of inspection. Corrective Action: Please ensure the pH is maintained between 7.2-7.4. |
104 | Improper Turnover of Flow Rate Observation: Flow metre was observed to be inoperable at the time of inspection. Corrective Action: Repair or replace as needed to ensure flow metre is able to correctly display the flow. |