Inspection Information:
Facility Type: | Swimming Pool/Waterslide (>19 sq.m) |
Inspection type: | Routine |
Inspection date: | May 17, 2011 |
Follow-up Required: | No |
This facility was given a low hazard rating.
More information on hazard ratings.
Chlorine (Total) |
Chlorine (Free Available) |
Chlorine (Combined) |
Bromine (Free Available) |
pH |
Total Alkalinity |
Total Hardness |
Temperature |
Clarity |
Cyanuric Acid |
Violations:
A summary of the violations found during the inspection are listed below.
Code | Description / Observation / Corrective Action |
421 | Other (specify below) Observation: Combined chlorine: total chlorine - free chlorine = (7.6ppm - 4.7ppm = 2.9ppm) Corrective Action: Ensure combined chlorine is less than 1ppm so free chlorine can work more effectively (note: operator shocked the pool on Fridays) |