Smithers Community Water System - Inspection Report

Inspection Information:
Facility Type:  WS1A
Inspection type:  Routine
Inspection date:  September 08, 2017
Follow-up Required:  Yes

This facility was given a moderate hazard rating.
More information on hazard ratings.

Violations:
A summary of the violations found during the inspection are listed below.

Code   Description / Observation / Corrective Action
308  Critical Contamination of finished water - Mains
Observation: Total coliform counts have occured in 7 of 26 samples since August 21, 2017 (26.92%)
Corrective Action: A boil water notice was issued by the Town of Smithers on Friday September 01, 2017. Identify source of contamination and remove and/or disinfect and flush system in an attempt to remove the souce of contamination. This process/procedure used should be that of an approved standard method of disinfection to ensure proper concentrations and times are being identified and measured thoughout the process.
320   Other (specify below)
Observation: Emergency Response Plan requires updates.
Corrective Action: An Emergency Response Plan is available but updates are required at this time. Review of the current plan should be completed by November 01, 2017.
320   Other (specify below)
Observation: Access to a responsible person to apply adverse water emergency response protocol required at all times.
Corrective Action: A system for coordination, outside normal operating hours, is required. A copy of the Emergency Response Plan is to be quickly accessible to all potentially responsible parties.
308  Critical Contamination of finished water - Mains
Observation: Total coliform counts have occured in 7 of 26 samples since August 21, 2017 (26.92%)
Corrective Action: A boil water notice was issued by the Town of Smithers on Friday September 01, 2017. Identify source of contamination and remove and/or disinfect and flush system in an attempt to remove the souce of contamination. This process/procedure used should be that of an approved standard method of disinfection to ensure proper concentrations and times are being identified and measured thoughout the process.
320   Other (specify below)
Observation: Emergency Response Plan requires updates.
Corrective Action: An Emergency Response Plan is available but updates are required at this time. Review of the current plan should be completed by November 01, 2017.
320   Other (specify below)
Observation: Access to a responsible person to apply adverse water emergency response protocol required at all times.