Inspection Information:
Facility Type: | Restaurant |
Inspection type: | Follow-Up |
Inspection date: | July 06, 2011 |
Number of critical violations: | 0 |
Number of non-critical violations: | 0 |
Follow-up Required: | Yes |
Violations:
No violations were found during the inspection
Comments:
The following items have been completed:
- New stainless steel prep tables have been purchased.
- Floor plans have been submitted
- Refrigerated pizza prep table has been purchased.
Operator is still undergoing renovations. A follow-up inspection will be conducted August 2, 2011 to ensure upgrades/renovations are completed, according to letter issued to operator dated October 10, 2010.