Inspection Information:
Facility Type:Restaurant
Inspection type:Routine
Inspection date:April 01, 2008
Number of critical violations:2
Number of non-critical violations:  1
Follow-up Required:  Yes

Violations:
A summary of the violations found during the inspection are listed below.

Code   Description / Observation / Corrective Action
105  Critical Inadequate Cooling & Refrigerated Storage of Potentially Hazardous Food(s)
Observation: The temperature of the pizza freezer was noted at a higher temperature than -18C
Corrective Action: This should now be investigated and repaired/adjusted.
108  Critical Improper Cleaning, Sanitizing of Equipment and Utensils
Observation: The general cleaning was poor.
Corrective Action: Walls, floors and work equipment should now and routinely be thoroughly cleaned. I recommend that the lighting in this area be assessed for improvement to assist in cleaning.
116   Improper Construction / Maintenance of Establishment
Observation: The door edge gaskets and the door handles of the pizza line fridge were damaged.
Corrective Action: These should now be replaced to assist with temperature control and cleaning.
116   Improper Construction / Maintenance of Establishment
Observation: There are damaged floor areas in front of the pizza line station and near to the kettle where the seams have lifted.
Corrective Action: These areas should now be repaired/replaced leaving a smooth, impermeable and cleanable surface.

Comments: